Working on the Excavation with the Bobcat 8/17
The Depot - Museum passageway Project
Photos and Video's of our progress
Removing ramp deck and the vegetation 8/16
Dirt bank and stone removed, ready to dig for foundation 8/17
Reroute the drain system and add a basin drain.
Starting on Foundation Forms 8/18
Pouring the cement for footing and foundation walls 8/20
Under Floor framing completed 8/23
Flooring and framing in progress 8/24
Framing for door and window / depot roof cut back 8/25
Walls paneled and Cricket roof installed 8/28
some trim and wainscot for the stairs 9/1
Electrical circuits run, waiting for inspection 9/9
Linda came by and stained upper floor and staircase space 9/10
Started on drain wrap and siding outside 9/12
Window placement and siding primed both sides.
Stairs stained and ready for railings 9/17
door for museum classroom and framing 9/17
Getting the primer and trim paint done
prepping the class room for paint